California refinery integration by mid-2017, Port of Vancouver complete by end of 2017
Business News | By Kristin Hayes, Wed Dec 9, 2015 11:24am ESTIndependent refiner Tesoro Corp (TSO.N) has pushed the completion of integrating its California refineries to mid-2017 from early that year, according to a company presentation.
The expected cost of the project to combine the Los Angeles-area refineries is $460 million, up from a range of $400 million to $425 million.
The company also said it expects a $200 million railport project in Washington state to be finished in late 2017. The project to move up to 360,000 barrels per day via rail to the Port of Vancouver would be the biggest oil-by-rail project in the United States.